A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work.

1 Answer

+1 vote
by (30.8k points)
selected by
 
Best answer

Number of days A required do a piece of work : 16 

Number of days B required do a piece of work : 12

Work done by A in one day: \(\frac{1}{16}\)

Work done by B in one day: \(\frac{1}{12}\)

A works alone for 2 days, so work completed by A in 2 days : \(2\times\frac{1}{16}=\frac{1}{8}\)

Work left = \(1-\frac{1}{8}=\frac{7}{8}\)

Work done by A and B together in one day: \(\frac{1}{16}+\frac{1}{12}=\frac{7}{48}\)

They can do the work together in \(\frac{48}{7}\) days.

But \(\frac{7}{8}\)th of the work is done by both A and B

∴ Time required to complete \(\frac{7}{8}\)th of the work together by A and B : \(\frac{7}{8}\times\frac{48}{7}\) = 6 days

∴ Time taken to finish the work 6 + 2 = 8 days ( here 2 is added because\(\frac{1}{8}\)work is done by A alone).

∴ Total time taken to finish the work: 8 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.