A can do a piece of work in 15 days. B is 50% more efficient than A. B can finish it in 

A. 10 days

B. \(7\frac{1}{2}\) days

C. 12 days

D. \(10\frac{1}{2}\) days

1 Answer

+1 vote
by (29.9k points)
selected by
 
Best answer

Number of days required by A to finish the work : 15 days

Work done by A in one day: \(\frac{1}{15}\)

B can work 50% more efficiently than A,

∴ B's one day work = 150% of = \(\frac{150}{100}\times\frac{1}{15}=\frac{1}{10}\)

∴ B alone can complete the work in 10 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.