A and B can complete a piece of work in 12 days and 24 days respectivley. After A had worked for 6 days, B joined him and then they completed the work. How much should A receive as his share from the total amount of ₹ 180 paid for completing the work?
A. ₹120
B. ₹135
C. ₹100
D. ₹150

1 Answer

0 votes
by (106k points)
selected by
 
Best answer
Correct Answer - D
Let A works for x days, then B works for (x-6) days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.