Y is thrice as efficient as Z who is half as efficient as X,X,Y and Z can complete a job in 25 days. Find the time in which X and Y can complete it (in days)
A. 30
B. 36
C. 40
D. 45

1 Answer

0 votes
by (88.7k points)
selected by
 
Best answer
Let the time in which X,Y and Z can complete the job be x days, y days and z days respectively.
`(1)/(y)=3((1)/(z)) and (1)/(z)=(1)/(2)=((1)/(x))`
`:. y=(z)/(3) and x=(z)/(3)`
`(1)/(x)+(1)/(y)+(1)/(x)=(1)/(25)`
`(2)/(z)+(3)/(z)+(1)/(z)=(1)/(25)=rArrz=150`
`:. y50 an x=75`
X and Y can complete it in `((75)(50))/(75+50)` days =30 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.