A group of 5 people can do a piece of work in certain number of of days. If 4 more people join the group, they take 12 days less to do the same work. In work days can a group of 3 people do the work ?
A. 30
B. 45
C. 15
D. 60

1 Answer

0 votes
by (88.7k points)
selected by
 
Best answer
Correct Answer - B
(i) Use `M_(1)D_(1)=M_(2)D_(2)`
(ii) Let five people do the piece of work in x days. Find x.
(ii) `5(x)=9(x-12)`
(iii) Let three people do the same work in y days.
(v) Use, `5xx x=3xxy` and find y

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.