A certain job can be performed by 10 men in 24 days working 8 hours a day. How many days would be needed to perform the same job by 8 men working 12 hours a day?

1 Answer

+1 vote
by (35.0k points)
selected by
 
Best answer

It is given that the job can be performed by 10 men in 24 days by working 8 hours a day.

Let x be the number of days required by 8 men to perform the same job working 12 hours a day.

Since, the total time required to perform the job in both the cases is same.

\(\therefore\) 8 men would require 20 days to perform the same job working 12 hours a day.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.