A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.

1 Answer

+1 vote
by (60.2k points)
selected by
 
Best answer

Let B takes x days to complete the work.

Therefore, A will take (x-10) days

Number of days to complete the work by 

B cannot be less than that by A; therefore, we get: x = 30 

Thus, B completes the work in 30 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.