Identify the Method used for the dewatering of the foundation trenches.

(a) Pumping

(b) Freezing process

(c) Electro osmosis process

(d) Well Point System

1 Answer

0 votes
by (120k points)
selected by
 
Best answer
Correct answer is (d) Well Point System

Easiest explanation: Well Point System consists of a well points, riser, swinger arm, and header. The area to be devoted is surrounded by number of well points. The minimum spacing between the well points is 1 m.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.