In a pre-tensioned prestressed concrete cross-section,

Statement 1: The stress in wires is assumed to be zero at the end supports and increases to its final maximum value over its transmission length.

Statement 2: The bond stress between concrete and prestressed wires is maximum near the end supports and decreases to nearly zero over its transmission length.


1. Statement 1 and 2 are true
2. Statement 1 is true and statement 2 is false
3. Statement 1 is false and statement 2 is true
4. Statement 1 and 2 are false

1 Answer

0 votes
by (106k points)
selected by
 
Best answer
Correct Answer - Option 1 : Statement 1 and 2 are true

Concept:

Pre-tensioned prestressed concrete:

  • The stress in wires is assumed to be zero at the end supports and increases to its final maximum value over its transmission length.
  • The different stages involved in pre-tensioning are depicted.
  •  In the first stage, the tendons are stretched to the required tension and anchored to the rigid supports known as bulkheads (Stage 1).
  • Then the concrete member is cast around the tendons (Stage 2).
  • During the curing process, a bond develops between the tendon and concrete.
  • When the concrete attains sufficient strength, the tendons are released from the bulkheads (Stage 3).
  • Immediately after release, the tendons try to return to their original length.
  • But the bond between the steel and concrete prevents this movement thereby forcing the concrete into compression.
  • Since in the pre-tensioning method, the prestressing force from the tendon is transferred to concrete by bond.
  • The bond stress between concrete and prestressed wires is maximum near the end supports and decreases to nearly zero over its transmission length.
  • pre-tensioned members usually have large numbers of prestressing steel of smaller diameter so as increase the area of contact.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.