In a pre-tensioned prestressed concrete cross-section,
Statement 1: The stress in wires is assumed to be zero at the end supports and increases to its final maximum value over its transmission length.
Statement 2: The bond stress between concrete and prestressed wires is maximum near the end supports and decreases to nearly zero over its transmission length.
1. Statement 1 and 2 are true
2. Statement 1 is true and statement 2 is false
3. Statement 1 is false and statement 2 is true
4. Statement 1 and 2 are false