Equation for cement requirement in tones for four-story R.C.C. framed building (super structure) recommended by C.B.R.I is
1. 0.153 A + 0.57
2. 0.145 A + 0.54
3. 0.182 A – 0.35
4. 2.26 A + 66.8

1 Answer

0 votes
by (106k points)
selected by
 
Best answer
Correct Answer - Option 3 : 0.182 A – 0.35

Concept:

  • CBRI has recommended the following formulae which after a study of the specifications have been selected for this analysis.
  • The table as given below is for buildings of different shapes and plinth areas varying from 30 to 300 sq. these are the average constant.

 

Materials

Equations

Labours
(in days)

Equations

Cement(tones)

0.0204A- 0.014

Mason

0.023A

Sand (cu.m.)

0.036A

Carpenter

0.05A

Coarse aggregate (cu.m.)

0.071A-0.01

Blacksmith

-1.6+0.1A-0.0003A2

Steel (kg)

-171+10.46A-0.041A2

Mazdoor

0.343A


Where, A = Plinth area in sq.

Option 3 is close to the given equation by CBRI for cement. Hence, option 3 is correct.

  • This information is useful for the preparation of the building cost index, preplanning of materials, and labour requirement in a building project. Equations for Materials & Labour requirement for structure in Four-storeyed (RCC Frames Building),

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.