Match List 1 and List 2 and select the correct answer using the codes given below:
List-1
|
List-2
|
A. Cut-off trench of a dam to be constructed across the flowing river
|
1. Cellular sheetpile cofferdam
|
B. Shallow foundation of a bridge pier foundation work
|
2. Embankment type cofferdam
|
C. Sequential repetition of underwater foundation work
|
3. Single wall sheetpile cofferdam
|
D. Control of groundwater to prevent entry into a deep excavation
|
4. Floating steel cylinder cofferdam
|
1. A – 4, B – 3, C – 2, D - 1
2. A – 2, B – 1, C – 4, D - 3
3. A – 2, B – 3, C – 1, D - 4
4. A – 3, B – 4, C – 2, D - 1