In PERT, how much probability is considered for expected activity duration?
1. 33%
2. 50%
3. 67%
4. 99%

1 Answer

0 votes
by (106k points)
selected by
 
Best answer
Correct Answer - Option 2 : 50%

Concept-

Probability Factor is given by

\(z = \frac{{x - \bar x}}{\sigma }\)

Where,

σ is Standard Deviation

x is mean

For,

 z = 0, P (Z) = 50 %

Z < 0, P (Z) < 50 %

Z > 0, P (Z) > 50%

When expected activity duration is considered then the probability factor z = 0. So 50% probability is considered for expected activity duration.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.