In case of big projects, a certain amount to the extent of about 1.5% to 2% of the estimated cost is provided in the estimate as
1. Work charged establishment
2. Revised estimates
3. Supplementary estimate
4. Annual estimate

1 Answer

0 votes
by (103k points)
selected by
 
Best answer
Correct Answer - Option 1 : Work charged establishment

Explanation:

Work charged establishment charges includes temporary establishments as are employed for the execution or the intermediate technical supervision or departmental stores and machinery in connection with a specific work.

For such work charged establishment an amount of 1.5% to 2% is sanctioned.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.