Correct Answer - Option 1 : 44.44%
Given:
B is 4/3 times as efficient as A. If A can complete 5/8th of a given task in 15 days.
Concept used:
Time and work
Calculation:
B is 4/3 times as efficient as A
Efficiency of A : B = 3 : 4
Time of A : B = 4 : 3
A can complete 5/8th of a given task in 15 days
So, A completes whole task in 24 days.
4 unit = 24 days
3 unit = 18 days.
B works on it independently for 10 days.
so work remaining = 8 days
Remaining work = (8/18) × 100 = 44.44%