Mobilization advance up to certain percentage of cost of work is given to a contractor
1. On commencement of work at site for payment of loan taken by him
2. For the purchase of construction materials
3. For the payment of advances to labour and other staff
4. For all activities required to start the work at site on finalization of the contract documents

1 Answer

0 votes
by (103k points)
selected by
 
Best answer
Correct Answer - Option 4 : For all activities required to start the work at site on finalization of the contract documents

Explanation:

(i) Mobilization advance up to 10% of Tendered Amount” shall be paid to the contractor on submission of no revocable Bank Guarantee for an amount of 110% (One hundred ten percent) of an amount of mobilization advance demanded, from a nationalized / Scheduled Bank.

(ii) It is provided for all activities required to start the work at site on finalization of the contract documents.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.