For the task of estimating and costing, doors and windows are computed in
1. Running meter
2. Square meter
3. Cubic meter
4. Numbers

1 Answer

0 votes
by (103k points)
selected by
 
Best answer
Correct Answer - Option 4 : Numbers

Explanation:

Units of measurements: The units of measurement are mainly categorized for their nature, shape, and size and for making payments to the contractor. The principal of units of measurements normally consists of the followings:

(i) Single units of work like doors, windows, trusses etc., are expressed in numbers.

(ii) Works consisting of linear measurements involve lengths like cornice, fencing, handrail, bands of specified width, etc., and are expressed in running meter (RM).

(iii) Works consisting of areal surface measurements involve areas like plastering, whitewashing, partitions of specified thickness etc., are expressed in square meter (m2).

(iv) Works consisting of cubical contents which involve volumes like earthwork, cement concrete, masonry, etc., are expressed in cubic meters.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.