Correct Answer - Option 2 : 20 days
GIVEN:
Seema's time = 36 days
Ajay's time = 45 days
FORMULA USED:
Work = efficiency × time
CALCULATON:
Let total work be 1 unit
Seema's efficiency = 1/36 unit
Ajay's efficiency = 1/45 unit
Efficiency together = 1/36 + 1/45 = 9/180 = 1/20 unit
∴ time taken to complete = 20 days (efficiency = work/time)
∴ 20 days will be taken
ALTERNATE SOLUTION:
Let total work be 180 (L.C.M 0f 36,45)
Seema's efficiency = 180/36 = 5
Ajay's efficiency = 180/45 = 4
Efficiency together = (5 + 4) =9
Time taken = 180/9 = 20 days
∴ 20 days will be taken