X and Y can finish a work in 15 days and 30 days respectively. Both of them worked for 5 days and left. The remaining work was completed by Z in 5 days. Find total time taken to complete the work, if X and Z complete the work.
1. 7
2. 6
3. 8
4. 9

1 Answer

0 votes
by (102k points)
selected by
 
Best answer
Correct Answer - Option 2 : 6

Given:

X and Y can finish a work in 15 days and 30 days respectively. Both of them worked for 5 days and left. The remaining work was completed by Z in 5 days.

Formula:

If A and B can together finish it in t days with A and B finishing the work in a and b days respectively,

1/a + 1/b = 1/t

Calculation:

Let total work be 30 units, LCM of 15 and 30.

Efficiency X = 30/15 = 2

Efficiency Y = 30/30 = 1

Let the efficiency of Z be z

 ATQ,

⇒ 5(2 + 1) + 5z = 30

⇒ 15 + 5z = 30

⇒ 5z = 15

⇒ z = 3

∴ Required time = 30/3 + 2 = 30/5 = 6 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.