Three workers A, B and C started working on a construction field. Worker A can do the job in 25 days while B is 25% more efficient than A and C takes 80% more time than the time taken byy A and B when working together. If together they received Rs.19,600 for a week what is monthly salary of worker A?

 


1. Rs.1,68,000
2. Rs.30,000
3. Rs.24,000
4. Rs.1,50,000
5. Rs.8000

1 Answer

0 votes
by (102k points)
selected by
 
Best answer
Correct Answer - Option 3 : Rs.24,000

Time take by A to complete the work = 25 days

Time taken by B to complete the work = 25 × (100/125) = 20 days

C's one day work = (1/25 + 1/20) × (100/180) = (9/100) × (100/180) = 1/20

∴ Time taken by C to complete the work = 20 day

Ratio of time taken by A, B and C = 25 ∶ 20 ∶ 20 = 5 ∶ 4 ∶ 4

⇒ Efficiency of A, B and C = 4 ∶ 5 ∶ 5

Weekly income of the three workers = Rs.19,600

⇒ Daily income of the workers = 19,600/7 = Rs.2800

∴ Daily income of A = (4/14) × 2800 = Rs.800

⇒ Monthly income of A = 800 × 30 = Rs.24000

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.