Correct Answer - Option 2 : 0.75
Concept:
The relation between discharge (Q), velocity of flow (V) and area of cross section (A) is given as:
Q = A × V
Calculation:
Given:
Maximum permissible discharge, Q = 0.9 m3/sec.
Allowable velocity of flow, V = 1.2 m/s
Q = A × V
Or
0.9 = A × 1.2
∴ Area of cross section required, A = 0.75 m2.
Note:
As per Manning’s formula, the velocity of flow is given as:
\(V = \frac{1}{N}\;{R^{2/3}}{S^{1/2}}\)
Where,
N is the roughness coefficient
S is the bed slope
R is hydraulic depth which is the ratio of wetted area to wetted perimeter.