Working every day 8 hours 10 men can build 18 toys in 3 days. In how many days 24 men can build 15 toys at the rate of 6 hours per day work?


1. 1
2. 2
3. 3
4. 4

1 Answer

0 votes
by (95.6k points)
selected by
 
Best answer
Correct Answer - Option 2 : 2

Given:

Working every day 8 hours 10 men can build 18 toys in 3 days

Concept Used:

If M1 man can do W1 work in D1 days by working daily T1 hours and M2 man can do W2 work in D2 days by working daily T2 hours then, M1 × W1 × D1 × T1 = M2 × W2 × D2 × T2

Calculation:

Here,

M1 = 10, W1 = 18, D1 = 3, T1 = 8

and M2 = 24, W2 = 15, T2 = 6

Let, D2 = x

Then,

M1 × W1 × D1 × T1 = M2 × W2 × D2 × T2

⇒ 10 × 18 × 3 × 8 = 24 × 15 × 6 × (x)

⇒ x = 2

In 2 days, they can complete the work.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.