Correct Answer - Option 4 :
Load factor = 0.7058
Annual energy: 0.3 × 10
6 MWh
Concept:
Load factor: The ratio of average load to the maximum demand during a given period is known as the load factor.
Load factor = average load/maximum demand
= Units generated in T hours/ (T × Maximum demand)
Utilization factor: It is the ratio of maximum demand on the power station to the rated capacity of the power station.
Utilization factor = maximum demand / rated capacity
Plant capacity factor: It is the ratio of actual energy produced to the maximum possible energy that could have been produced during a given period.
Calculation:
Maximum demand = 50 MW
Capacity factor = 0.6
Utilization factor = 0.85
Utilization factor = 0.85 = 50/rated capacity
⇒ Rated capacity = 58.82 MW
Capacity factor = 0.6 = Actual energy/58.82
⇒ Actual energy = 35.29 MW
Number of hours in year = 8760
Energy generated per annum = 35.29 × 8760 = 0.3 × 106 MWh
Load factor = 35.29/50 = 0.7058