What is the method used for calculation of earthwork in road estimation?
1. All of the above
2. Mid-sectional area method only
3. Prismoidal formula method only
4. Mean sectional area method only

1 Answer

0 votes
by (108k points)
selected by
 
Best answer
Correct Answer - Option 1 : All of the above

Explanation:

  • Earthworks are engineering works created through the moving and/or processing of massive quantities of soil or unformed rock. 

  • Earthwork is done to reconfigure the topography of a site to achieve the design levels. Earthwork involves cutting and filling to achieve the required topography.

  • Following methods are used in the calculation of earthwork:

    • Prismoidal method

    • Trapezoidal method

    • Midsection area method

    • mean section area method 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.