Statement (I): Time-Cost Study for the project must be adopted only when project duration is to be crashed.

Statement (II): When there are unmanageable restrictions in realizing a predetermined resource histogram Time-cost Study may have to consider extension of project duration as well.
1. Both Statement (I) and Statement (II) are individually true and Statement (II) is the correct explanation of Statement (I)
2. Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)
3. Statement (I) is true but Statement (II) is false
4. Statement (I) is false but Statement (II) is true 

1 Answer

0 votes
by (101k points)
selected by
 
Best answer
Correct Answer - Option 2 : Both Statement (I) and Statement (II) are individually true but Statement (II) is not the correct explanation of Statement (I)

Crashing of project duration:

Crashing of project duration means that increasing the direct cost of the project and reducing the in direct cost of project. Therefore, to reach an optimum cost of a project, time-cost study is used in the Critical Path Method (CPM). 

Resource histogram is the graph between number of resource required and time. It is prepared before the beginning of construction activities. 

∴ Both statements are individually true.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.