In progress of a project, the percentage of error will be less in
1. Definitive cost estimate
2. Detailed estimate
3. Preliminary estimate
4. Study estimate

1 Answer

0 votes
by (101k points)
selected by
 
Best answer
Correct Answer - Option 1 : Definitive cost estimate

Explanation:

Definitive cost estimate provides an accurate estimate of project costs. It is used for making many purchasing decisions for which accurate estimates are required and for estimating final project costs. The accuracy of this type of estimate is normally -5 percent to +10 percent.

 

 

Life Cycle State

Type of Cost Estimate

1.

Initial (concept) stage

Rough order magnitude or Indicative cost estimate

2.

Planning and Design

Preliminary cost estimate

3.

Implementation or trending stage

Detailed cost estimate

4.

Closure stage

Definite cost estimate

 

As the project progress the error in cost estimation of the project decreases sharply from the rough order of magnitude estimates to definitive cost estimate.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.