An activity in a project management network is


1. The beginning or end of a specified job
2. An element of work entailed in the project
3. Represented by a circle in a network with a number in it
4. The progress of work up to a certain limit

1 Answer

0 votes
by (95.2k points)
selected by
 
Best answer
Correct Answer - Option 2 : An element of work entailed in the project

Activity:

Any portion of a project which consumes time or resources and has a definite beginning and an end is called as an activity.

It is denoted by an arrow, but the length of an arrow has no significance.

The symbol above the arrow indicates activity description and the number below indicates activity duration in time units.

Activity is actual performance of a job. It requires time and resources for its completion.

Parallel activities:

The activities which can be performed simultaneously and independent of each other called as parallel activities.

Successor activities:

Activities that can be performed after performance of other activity are known as successor activities.

Predecessor activities:

Activities that are required to be performed before another activity can begin are called as predecessor activities.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.