Which one of the following distributions provides information regarding the uncertainty of duration time estimates is PERT described network?
1. Beta-distribution
2. Normal distribution
3. Poisson distribution
4. Binomial distribution

1 Answer

0 votes
by (95.4k points)
selected by
 
Best answer
Correct Answer - Option 1 : Beta-distribution

PERT described networks are based upon three-time estimates namely ‘pessimistic time’, ‘optimistic time’ and ‘most likely time’. Three-time estimates are needed when the conditions are uncertain and one-time estimate is not enough. These three-time estimates are incorporated by the Beta distribution.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.