The processing times and the due dates of 4 independent jobs processed by a single machine in a shop are given in the table.

 Job 

 Processing time 

(days)

 Due date 

(in days)

1

4

6

2

7

9

3

2

18

4

8

15

 

The average lateness of the job (in days) following the shortest processing time (SPT) rule is _____.

1 Answer

0 votes
by (78.8k points)
selected by
 
Best answer

Concept:

In the SPT rule, jobs are sequenced in increasing order of their processing time i.e. minimum time first and maximum time in last.

Note: If two jobs have the same process time then job having less due date will be processed first.

Calculation:

In this question, arranging the jobs according to SPT rule.

 Jobs 

 Processing time 

 Due date 

 Completion time 

 Lateness  

3

2

18

0 + 2 = 2

0

1

4

6

2 + 4 = 6

0

2

7

9

6 + 7 = 13

4

4

8

15

13 + 8 = 21

6

Total lateness = 10 

\(Average\;lateness = \frac{{10}}{4} = 2.5\;days\;per\;job\)

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.