For a construction project the mean and standard deviation of the completion time are 200 days and 6.1 days respectively. Assume normal distribution and use the value of standard normal deviate z = 1.64 for the 95% confidence level. The maximum time required (in days) for the completion of the project would be ________

1 Answer

0 votes
by (152k points)
selected by
 
Best answer

\(\begin{array}{l} {\rm{Z}} = \frac{{{{\rm{T}}_{\rm{s}}} - {{\rm{T}}_{\rm{E}}}}}{\sigma }\\ 1.64 = \frac{{{T_s} - 200}}{{6.1}} \end{array}\)

Ts = 210 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.