A manufacturing shop processes sheet metal jobs, wherein each job must pass through two machines (M1 and M2, in that order). The processing time (in hours) for these jobs is:
Machine
|
Jobs
|
P
|
Q
|
R
|
S
|
T
|
U
|
M1
|
15
|
32
|
8
|
27
|
11
|
16
|
M2
|
6
|
19
|
13
|
20
|
14
|
7
|
The optimal make-span (in hours) of the shop is:
1. 120
2. 115
3. 109
4. 79