Use app×
Join Bloom Tuition
One on One Online Tuition
JEE MAIN 2025 Foundation Course
NEET 2025 Foundation Course
CLASS 12 FOUNDATION COURSE
CLASS 10 FOUNDATION COURSE
CLASS 9 FOUNDATION COURSE
CLASS 8 FOUNDATION COURSE
0 votes
179 views
in General by (115k points)
closed by

A set of 5 jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. K per day.

Job

Processing time

P

5

Q

2

R

3

S

2

T

1


A schedule that minimizes the total inventory cost is


1. T-S-Q-R-P
2. P-R-S-Q-T
3. T-R-S-Q-P
4. P-Q-R-S-T

1 Answer

0 votes
by (152k points)
selected by
 
Best answer
Correct Answer - Option 1 : T-S-Q-R-P

The total inventory cost is minimized when the jobs are processed according to the shortest processing time. That is job with least processing time should be done first.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

Categories

...