Twelve men can complete a task in 16 days. Thirty-two women can complete the same task in 12 days. Eight men and eight women together worked for 12 days, after which the women dropped and 8 men joined. In how many days the men will be able to complete the remaining task?
1. 3 days
2. 9 days
3. 10 days
4. 2 days

1 Answer

0 votes
by (110k points)
selected by
 
Best answer
Correct Answer - Option 1 : 3 days

Given:

Time taken by 12 men to do a task = 16 days 

Time taken by 32 women to do the same task = 12 days 

Formulas used:

Total work = (No of persons) × Time 

Calculation:

12 men × 16 days = 32 women × 12 days 

⇒ 1 Man = 2 Women 

Total work in terms of men = 12 × 16 = 192 units 

Work done by (8 men + 8 women) in 12 days = (8 men + 4 men) × 12 = 12 × 12 = 144 units 

Remaining work after which women left = 192 units - 144 units = 48 units 

Now, 8 more men joined, total men will be (8 + 8) = 16 

∴ No of days taken by 16 men to complete the remaining task = 48 units/16 

⇒ 3 days 

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.