Match the following types of formworks with their minimum required striking period.
a.
|
16-24 hours
|
1.
|
Soffit formwork to slabs
|
b.
|
7 days
|
2.
|
Props to beams and arches spanning up to 6 m
|
c.
|
14 days
|
3.
|
Vertical formwork to columns, walls, and beams
|
d.
|
3 days
|
4.
|
Props for slabs spanning up to 4.5 m
|
1. a - 3, b - 2, c - 4, d - 1
2. a - 4, b - 3, c - 2, d - 1
3.
a - 3, b - 4, c - 2, d - 1
4. a - 3, b - 4, c - 1, d - 2