Match the column.
a.
|
Detailed estimate
|
1.
|
Estimate of additional works during the process
|
b.
|
Supplementary estimate
|
2.
|
Prepared for approx. rates initially
|
c.
|
Revised estimate
|
3.
|
Includes details and cost of everything
|
d.
|
Rough estimate
|
4.
|
Prepared when the costs exceed more than 5%
|
1. a - 2, b - 1, c - 4, d - 3
2. a - 3, b - 4, c - 1, d - 2
3. a - 3, b - 1, c - 4, d - 2
4. a - 1, b - 3, c - 4, d - 2