Correct Answer - Option 2 : It does not take uncertainties involved in the estimation of times.
Explanation:
PERT stands for "Project Evaluation and Review Technique". This network model is used for project scheduling.
Difference between PERT and CPM (Critical Path Method)
PERT
|
CPM
|
1. Probabilistic approach
|
1. Deterministic approach
|
2. Three-time estimate
|
2. One-time estimate
|
3. Event oriented network model
|
3. Activity-oriented network model
|
4. The slack concept is used
|
4. Float concept is used
|
5. Project crashing is not possible
|
5. Project crashing is possible
|
6. Deals with probabilistic time estimates.
|
6. Deals with deterministic time estimates.
|
PERT does take uncertainties involved in the estimation of times, therefore three-time estimates have been taken for the calculation project duration. They are optimistic (to), pessimistic (tp), and most likely (tm).
\(T_e=\frac{t_o\;+\;4t_m\;+\;t_p}{6}\)
Therefore, the option 2 is the incorrect statement among the given options.