‘P’ is twice as good a workman as ‘Q’ and together they finish a piece of work in 48days. In how many days will ‘P’ alone can finish the work?
1. 68 days
2. 74 days
3. 72 days
4. 70 days

1 Answer

0 votes
by (111k points)
selected by
 
Best answer
Correct Answer - Option 3 : 72 days

Given:

1/P + 1/Q = 1/48

Calculation:

Let time taken by P be a days and time taken by Q be 2a days.

⇒ 1/a + 1/2a = 1/48

⇒ 3/2a = 1/48

⇒ a = 72

∴ In 72 days, P alone can finish work.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.