Correct Answer - Option 2 : 6 days
Given:
Time taken by A to finish a task alone = 24 days
Calculation:
Let the total work be = 1
A alone can finish the task in 24 days
⇒ A's one-day work = 1/24
A and B complete the whole task in = \(11 \frac{1}{3}\) days
A and B work on alternate days, with B beginning so, we can say B will work only 6 days
⇒ A will work only \(11 \frac{1}{3}\) - 6 = \(5 \frac{1}{3}\) days
If A's one day work = 1/24 of work A completes in 1 day
⇒ A's \(5 \frac{1}{3}\) days work = 1/24 × \(5 \frac{1}{3}\) = 1/24 × 16/3
⇒ 2/9
Remaining work = 1 - 2/9 = 7/9
∴ B does the 7/9th part of the work in 6 days.
Note-
B, A, B, A, B, A, B, A, B, A, B, A/3
B completely 6-day work
That's why we have taken the 6 days work by B alone.