Which of the following networks is activity-oriented?


1. PERT
2. CPM
3. Both 1 and 2
4. None of the above

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 2 : CPM

Concept:

PERT stands for "Program Evaluation and Review Technique"

CPM stands for "Critical Path Method"

Difference between PERT and CPM:

PERT

CPM

 1. Probabilistic approach

 1. Deterministic approach

 2. Three-time estimate

 2. One-time estimate

 3. Event oriented network   model

 3. Activity-oriented network
 model

 4. The slack concept is used

 4. Float concept is used

 5. Project crashing is not possible

 5. Project crashing is possible

 6. Deals with probabilistic time estimates

 6. Deals with deterministic time   estimates

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.