Correct Answer - Option 2 : 2 days
Given:
A, B and C can complete a work in 12 days,15 days and 24 days respectively.
Formula used:
Total work = Efficiency × Time
Calculation:
Let total work be 1 unit
Work done by A in 2 days = 2/12 unit
Work done by (A + B) in 5 days = 5 × {(1/12) + (1/15)} unit
⇒ 5 × 9/60 unit
⇒ 9/12 unit
So, remaining work = 1 - {(2/12) + (9/12)} unit
⇒ 1- (11/12) unit
⇒ 1/12 unit
So, time taken by C to complete 1/12 work = (1/12)/(1/24) days
⇒ 24/12 days
⇒ 2 days
∴ C complete remaining work in 2 days.