Karan completed the school project in 33 days. How many days will Soham take to complete the same work if he is 45% more efficient than Karan?


1. 25.40
2. 30.33
3. 22
4. 35
5. 22.75

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 5 : 22.75

Given:

Time taken by Karan to do the school project is 33 days.

Efficiency of Soham is 45% more than Karan.

Formula Used:

Total work = Total number of days × Efficiency

Calculation:

Let Karan’s efficiency to complete the work be 100

⇒ Soham’s efficiency to complete the work will be 145

Now Karan took 33 days to complete the work,

⇒ Total work = 100 × 33

⇒ Total work = 3300 units

To complete 3300 units of work Karan will take,

⇒ 3300/145

⇒ 22.75 days. 

∴ Time taken by Soham to complete the school project is 22.75 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.