Correct Answer - Option 2 : 3 days
Given:
8 men and 2 women can do a piece of work in 24 days
16 men in 8 hours is equal to the work done by 2 women in 24 hours
Formula:
Total work = Efficiency × Time Taken
Calculation:
Let efficiency of 1 man and 1 woman be M and W respectively
According to the question,
(8M + 2W) × 24 = Total work ----(1)
Now,
16M × 8 = 2W × 24
⇒ 8M = 3W
Putting the value of 8M = 3W in equation (1),
(8M + 2W) × 24 = Total work
⇒ (3W + 2W) × 24 = 120 W
Then,
8M = 3W
⇒ (8M) × 5 = (3W) × 5(Multiplying both sides with 5)
⇒ 40M = 15W
Again, According to the question,
(40M + 45W) × d = 120W × 1.5
⇒ (15W + 45W) × d = 120W × 1.5
⇒ 60W × d = 120W × 1.5
⇒ d = 3 days
∴ The required time will be 3 days.