Ravi completed the school project in 30 days. How many days will Raushan take to complete the same work if he is 25% more efficient than Ravi?
1. 18
2. 20
3. 22
4. 24

1 Answer

0 votes
by (115k points)
selected by
 
Best answer
Correct Answer - Option 4 : 24

Given:

Time taken by Ravi to complete the work = 30 days

Raushan is 25% more efficient than Ravi

Calculation:

Let the days taken by Raushan to complete the work be x

The ratio of time taken by Raushan and Ravi = 125 ∶ 100 = 5 ∶ 4

⇒ 5 ∶ 4 = 30 ∶ x

⇒ x = (4 × 30)/5 = 24

∴ Raushan will completed the same work in 24 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.