Correct Answer - Option 4 : 24
Given:
Time taken by Ravi to complete the work = 30 days
Raushan is 25% more efficient than Ravi
Calculation:
Let the days taken by Raushan to complete the work be x
The ratio of time taken by Raushan and Ravi = 125 ∶ 100 = 5 ∶ 4
⇒ 5 ∶ 4 = 30 ∶ x
⇒ x = (4 × 30)/5 = 24
∴ Raushan will completed the same work in 24 days