Given below item describes a situation and is followed by four possible response. Indicate the response you find most appropriate. Choose only one response for each item. The responses will be evaluated based on the level of appropriateness for the given situation.

Please attempt the item, there is no penalty for wrong answer for these items.

You are handling a time-bound project, During the project review meeting, you find that the project is likely to get delayed due to lack of cooperation of the team members, You would...


1. Warn the team members for their non-cooperation.
2. Look into reasons for non-cooperation.
3. Ask for the replacement of team members.
4. Ask for extension of time citing reasons.

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 2 : Look into reasons for non-cooperation.

Situation: You are handling a time-bound project, During the project review meeting, you find that the project is likely to get delayed due to lack of cooperation of the team members, You would.

Analysis of options:

Statement

Correctness

Reasoning

Warn the team members for their non-cooperation.

 Incorrect

This would be irresponsible. Warning may not be effective and team members may continue same behaviour which may result in delay in the project.

Look into reasons for non-cooperation.

 Correct

This would be the correct course of action. As it would be responsible, rational on your part to warn your team members and take control of situation at the right time.  

Ask for the replacement of team members.

 Incorrect

This will show your incompetence to handle your team and lack of leadership qualities.

Ask for extension of time citing reasons.

 Incorrect

 This will show your incompetence to handle your team and lack of leadership qualities and time management qualities.

Hence, 'Look into reasons for non-cooperation.' is the correct answer.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.