Arjun completes a (5/7)th of a given work in 25 days. At the same rate, how many more days he will take to complete the remaining work?
1. 6 days
2. 7 days
3. 10 days
4. 5 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 3 : 10 days

Given

Arjun completes (5/7)th of work in 25 days.

Calculation

Let the number of days requires to complete the remaining work is x days

Remaining work = [1 - (5/7)]

⇒ (7 - 5)/7

⇒ 2/7

(5/7) : (2/7) : : 25 : x

⇒ (5/7) × x = (25) × (2/7)

⇒ x = (25 × 2)/5

⇒ x = 10

∴ 10 days are required to complete the remaining work.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.