A house to be built in 80 days by a contractor. He hired 100 men for the work in beginning and 100 more after 70 days and completed the house on time. If contractor did not hire any extra men for the work, find the delay in the work.  


1. 12 dyas
2. 10 days
3. 15 days 
4. 16 days
5. 18 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 2 : 10 days

Given:

Days taken to built a house = 80 days

Men worked for first 70 days = 100 

Men worked after 70 days  = 200 

Formula Used:

Men1 × Efficiency1 × Days1/Work1 = Men2 × Efficiency2 × Days2/Work2

Calculation:

After 70 days

The remaining work completed by 200 men in 10 days

⇒ 100 men will complete this work in

⇒ 200/100 × 10 = 20 days

⇒ The delay in work

⇒ (70 + 20) - 80 = 10 days

∴ If he didn't hire extra workers there will be delay of 10 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.