Correct Answer - Option 2 : 10 days
Given:
Days taken to built a house = 80 days
Men worked for first 70 days = 100
Men worked after 70 days = 200
Formula Used:
Men1 × Efficiency1 × Days1/Work1 = Men2 × Efficiency2 × Days2/Work2
Calculation:
After 70 days
The remaining work completed by 200 men in 10 days
⇒ 100 men will complete this work in
⇒ 200/100 × 10 = 20 days
⇒ The delay in work
⇒ (70 + 20) - 80 = 10 days
∴ If he didn't hire extra workers there will be delay of 10 days.