Sunita can finish a project in 21 days and Sarita can finish the same project in 15 days. Sarita worked for 10 days and left the job. How many days would it take Sunita to finish the remaining work alone?
1. 10 days
2. 7 days
3. 12 days
4. 11 days
5. 8 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 2 : 7 days

Given  

Sunita can finish a project in = 21 days

Sarita can finish the same project in = 15 days

Sarita worked on the project for days = 10 days

Formula used 

Work = Time × Efficiency 

Calculation

Sarita’s 10 days work = 1/15 × 10 = 2/3

Remaining work = 1 - (2/3) = 1/3

Sunita can finish a project in = 21 days

Now ,

1/21 Work done by Sunita in = 1 day

1/3 works can be done by Sunita in = 21 × 1/3 = 7 days

∴ Sunita will finish the remaining work in 7 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.