Correct Answer - Option 3 : 2 women
Given:
M1 = 8
M2 = ?
D1 = 10 days
D2 = 40 days
W1 = W2 = 1
Formula Used:
M1D1W2 = M2D2W1
Calculation:
M1D1W2 = M2D2W1
⇒ 8 × 10 × 1 = M2 × 40 × 1
⇒ M2 = 8 × 10/40
⇒ M2 = 2 women
∴ 2 women can complete a work in 40 days.