Correct Answer - Option 1 : 12 hours
Given:
M1 = 6
M2 = 8
T1 = 16 hours
T2 = ?
W1 = W2 = 1
Formula Used:
M1T1W2 = M2T2W1
Calculation:
M1T1W2 = M2T2W1
⇒ 6 × 16 × 1 = 8 × T2 × 1
⇒ T2 = 6 × 16/8
⇒ T2 = 12 hours
∴ 8 girls take 12 hours to complete painting a canvas.