Correct Answer - Option 3 : 12 days
Given:
Time taken by A and B = 30 days
Time taken by B and C = 24 days
Time taken by C and A = 20 days
Formula used:
Total work = Efficiency × time
Calculation:
Total work = (LCM of 30, 24, and 20)
Total work = 120 units
The efficiency of (A + B) = 120/30 = 4 units/day ...1)
The efficiency of (B + C) = 120/24 = 5 units/day ...2)
The efficiency of (C + A) = 120/20 = 6 units/day ...3)
From equations (1), (2) and (3), we get
A + B + B + C + C + A = 4 + 5 + 6
⇒ 2(A + B + C) = 15
⇒ (A + B + C) = 15/2 units/day ...4)
From equations (2) and (4), we get
A + 5 = 15/2
⇒ A = 5/2 units/day
Total work done by (A + B + C) in 12 days = 12 × (15/2)
⇒ 90 units
Remaining work = 120 - 90 = 30 units
Time taken by A to complete the remaining work = Remaining work/Efficiency of A
⇒ 30/(5/2) = (30 × 2)/5
⇒ 12 days
∴ Time taken by A to complete the remaining work in 12 days.