A piece of work can be done by 6 men and 5 women in 6 days or 3 men and 4 women in 10 days. It can be done by 9 men and 15 women in:
1. 8 days
2. 5 days
3. 3 days
4. 2 days

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 3 : 3 days

Given:

Time taken by 6 men and 5 women to complete the work = 6 days 

Time taken by 3 men and 4 women to complete the work = 10 days 

Calculation:

(6m + 5w) × 6 = (3m + 4w) × 10 

⇒ 36m + 30w = 30m + 40w

⇒ 6m = 10w

⇒ m/w = 5/3

Put m = 5 and w = 3 

Total Work = (6 × 5 + 5 × 3) × 6

⇒ 45 × 6 = 270

⇒ Time taken by 9 men and 15 women = 270/(9 × 5 + 15 × 3)

⇒ 270/90 = 3 days

∴ 9 men and 15 women can complete the whole work in 3 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.